3/5: Roofing Finished!

News, UpdatesLeave a Comment

Happy Friday Everyone! We had a great week this week! The weather was awesome! We continued with underground and overhead rough-ins, finished the block walls in the locker room area, continued patching precast walls, put … Read More

2/5: Two Slabs Poured

News, Updates

We had a pretty good week this week! We prepped and poured two slabs on grade! One in the Convention Center Conference and Meeting Rooms and one in the locker room area between the rinks … Read More